I had been putting this off as I was not sure of the best method of dealing with this damage.
I had a plan formulated but as we all know the best laid plans etc.
From the beginning here are a few pixs of the what was found inside the roof section using a USB camera.
The spots of rust are caused by two things, one is a nail gun used for pulling out damage in blind or difficult to reach panels and the second where you can see the Jap thinners can are from a pin welder. The other images show rust forming at the panel joints and at the D pillar.
https://goo.gl/photos/Jd1LMAYhtYSnYhpJA
The outside sections looked relatively good but with slight bubbling under the paint work.
The paint was removed using a abrasive mesh wheel on an angle grinder so as not to remove any metal. The filler on the front screen pillar area was 10 mm deep in some spots.
Heres what that revealed.
There were two patches, the foremost one was a very poorly executed repair that had been welded to the screen pillar interior panel and so blocked any form of drainage down the screen pillar interior. The second was the Jap thinners can made using a pin welder.
You can see in the last image the damage that was repaired using the pin puller, the little raised bumps along that area.
https://goo.gl/photos/4NiKkgDu9nEu3RAq8
The patches were removed to expose the underside.You can see the damage to the internal structure caused by the poorly repaired front patch.
The second tin can fix just covered a rust hole, had the repairer treated the underlying area before patching it would have made an acceptable repair. These repairs were from two different repairers I believe.
https://goo.gl/photos/VnBDTS94oMKgLp6KA
The gutter was badly corroded and rust had caused pinholes along the length of th roof panel along that side but mainly around the points where the internal structure had met the roof outer skin.
https://goo.gl/photos/pXsYmk8AE8EGi4CeA
Because of the poor front repair blocking the drainage route rot had set up around the screen pillar door shut.These images show that damage after the rusted sections had been removed.
https://goo.gl/photos/6Js7JJRqcHyPHrqd7
The Plan
Obviously the front interior structure would need to be made safe, as this is covered by the roof skin it was an easy one not having to worry to much about the cosmetics just the structure.
The outer skin of the roof panel gave a different set of problems there where a few options open to me such as capping or cold filling but as the corrosion was between the seams of the gutter it would need this area to be removed to see the extent, if any, of the damage to the underlying panels.
The rust to the rising portion of the roof skin above the gutter rose slightly higher than the first swage so I would cut this section just below the upper swage to leave about a 8mm lip to fix the new section to, the swage hopefully providing some stiffness to minimize distortion if it were to be welded instead of glued. The gutter section was to be removed by drilling out the spot welds with a special drill bit that cuts around the out side of the spot weld leaving the spot weld attached this is then removed by grinding.
I eventually decided on welding as I didnt feel confident that the narrow flange left after cutting out would be enough of a surface area for gleuing the panel in place given the stresses here and the additional weight of the awing.
These images show the preliminary cuts, the drill bit and the removal process. The horizontal cuts were made in three stages for reasons explained later.
https://goo.gl/photos/whfsByKXpNotSETGA
Repair panels
Also suspect was the screen surround flange given this and that the weld would be very close to the screen edge the screen was removed by Will the Windscreen. Fame at last!
The front section of the roof would be more awkward than the gutter panel as there is a flared compound curve at the crown and the rust had extended as far back as the upper gutter section of the AFT.
I had thought this would have to be made in three pieces but I was able to form it using two panels.
The numbers on the front section show the tacking points each one needed to be aligned before they could be finally continuously welded.
https://goo.gl/photos/uNzVQyeVvkdTVAGLA
The second section was actually the more difficult as it has raised part to meet in with the remaining sound upper AFT drain.
https://goo.gl/photos/2gMHSweEiFTBVe6S7
As the cut along the length of the roof skin was being made I noticed that the roof was droppingand pinching the cutting disc.
As I intended to reinforce the roof panel to support the addition of the awning I made three smaller cuts and welded in the reinforcements before cutting out the remainder.
The reinforcements were placed over, or close to, the B,C & D pillars.
These were made from 16SWG steel folded at the base to sit in the horizontal gutter section. They were stitch welded at the base and MIG plug welded through the outer roof skin.
The gutter repair section was made from 20SWG steel folded along its length, zinced and pinned into position before continuously edge welded along its length at the upper swage.
https://goo.gl/photos/ZnCvrXq2gLExZDhf7
The gutter horizontal section was drilled to allow for plug welding along its length 32 plugs were needed.
In one of the images you can see next to the hole the plug cut from the panel using the spot weld cutting bit.
Finally the MIG plug welds were ground to be level with the surface of the panel.
https://goo.gl/photos/kodNtUErqXQhmiH77
The front section of the roof was leaded and filed to shape and then polyester filled along with the roof flange weld.
Normally I would have left the filling to be carried out when the whole shell was being prepped for paint but as that is some time off I felt easier knowing that the roof area welds were sealed. in order to do this I would need to run the thinned zinc paint in between the repaired sections flanges and then I could wax inject the repairs and so seal up the interior welds that are not accessible with a paint brush.So the filler here would need to be applied first before that could be done.
A mucky business as you will see.
The gutter was blocked at either end and very thin mix of zinc paint flooded into the gutter allowing it to seep between the welds and as it turned out run all over the panel below it!
The excess was brushed over the filler to seal that also.
https://goo.gl/photos/Va3asvbkbUbtJasDA
Finally the D pillar patch was welded in place. I had intended to cold repair this but realized I had used the material on a previous job and as it is Saturday and the pub is open I welded the patch instead.

As for the screen flange there was nothing really to have worried about but as I have gone this far it was worth the cost of having it removed it has allowed me to clean back the small amount of rust and prep it for paint and I now have peace of mind that I have got everything.
My next job is to ensure that all is totally waxed up and sealed. The leveling for paint and the cosmetic stuff will come later..
Total time taken to get it to this stage is 260 hrs so at £62pph add to that materials and sundry items of 460.00 well you can do the maths.
However it keeps me off the streets and I can say that I have thoroughly enjoyed this chapter of the refurb.
Bongos are infectious are they not.
I will be fitting a Webasto Thermo Top heater as soon as work permits and at the risk of boring you lot to death I will cover that in another thread as well as the rest of the refurb.
I hope this lot has been of interest to some of you peeps and I apologies again for using links and not directly view-able images.
And that ladies and gents is that.....
